Improving of ventilation system of Anode compartment and connection to 120m stack
Client: Aurubis JSC.
Completed: 2015 December
Manufacturing, delivery and erection of steel structures.
Manufacturing, delivery and erection of Scrubber - Ø=4500mm.
Dismantle and erection of existing scrubber - Ø=2000mm.
Manufacturing, delivery and erection of air ducts Dn=450mm to Dn=2000mm, carbon and stainless steel shaped fittings and hoods.
Strengthening of the stack platform on elevation +32.00.